MaltaToday previous editions

MT Oct 6 2013

Issue link: https://maltatoday.uberflip.com/i/187071

Contents of this Issue

Navigation

Page 23 of 55

24 Opinion maltatoday, SUNDAY, 6 OCTOBER 2013 Court orders couple to pay contractor reduced fee for finishes O n 30 September 2013, Mr Justice Joseph Zammit McKeon ordered Mario and Theresa Camilleri to pay a contractor, IVN Holdings Limited, a reduced price for work carried out on their property, since it was concluded that the work had not been done well. IVN Holdings Limited sued the Camilleris for €94,702.36 for non-payment for work it had done on a Siggiewi property. IVN then reduced the claim to €69,357.17. The defendants pleaded that the agreement was to pay a deposit of 10%, then pay the balance when the works were concluded. They claimed that the company had not concluded and, therefore, payment was not due. They also claimed that the bills were inflated, as, for example, they were meant to pay for items including VAT, and the company charged them further VAT. They also claimed that the works were not done according to acceptable standards. They held that only €21,467 was due. The court appointed a technical expert to examine the invoices and the works. The expert pointed out that the parties had entered into an agreement that the Camilleris would pay Lm5,500 per apartment for finishes and installation of services. Four other agreements were signed between the parties. On 6 March 2008 a bill was presented stating that the works were completed. The couple's architect, Tancred Mifsud, presented in court a list of problems (or snag list) of reparatory works. It seems from Malcolm Mifsud mmifsud@mifsudadvocates.com.mt this list that no reparatory works were required with regard to gypsum on the walls and ceiling. Keith Attard Portughes testified regarding how Mr Camilleri had approached him to perform the works in a block of apartments. The agreement was for 40% settlement in cash and 60% barter. The company's foreman testified and admitted that there were some works that had to be done, but described also the differences that took place between his employer and the property owner. The court also quoted Mr Camilleri's testimony, wherein he described how he had visited the site a number of times and found "Arabs" working there. Camilleri would point out that the works were not being done correctly, and since there were around seven Arab workers, he was afraid and left. The court expert on site found a number of shortcomings and listed them for the court to consider. The expert concluded that the agreement mentioned only lump sums for every apartment and not itemised units. The agreement intended that the property be completely finished, however, this was not carried out professionally and in fact the costs for repair amounted to €5,130. Furthermore, there should be a further reduction of €1,400 on the bathrooms. The total bill was €119,779.02. The defendants paid €50,421.85, leaving a balance of €69,357.17 – however, the court expert calculated that the Camilleris should pay a lesser amount, €46,533. The court pointed out that although legally it is not bound by the court expert's conclusions, it cannot dismiss them lightly and must do so only on very serious grounds. Furthermore, the court noted that none of the parties contested the conclusions of the court expert in any manner. The court then analysed the agreements the parties had signed and held that they were an expression of their intentions, and if they were legally binding, then they could be revoked or changed only by another agreement. In fact Article 993 of the Civil Code states that contracts must be executed in good faith. The agreement mentioned only the desired end and not the unit price. If it were the unit price, then the contractor would have a right to be paid for the work The company accepted to carry out the pending snag list, but the defendants refused. On this ground the company was correct to file the action when it did carried out. If the price were fixed on the end product, then the contractor would be paid at the end when all the works were carried out. In this particular case, there was a disagreement when the works were being carried out and, therefore, the contractor did not manage to finish. As described by the court expert, the works carried out did not reach professional standards. The court noted on the other hand that the defendants had effected payments during the court case and did not file a counter-claim for damages. Furthermore, the company had accepted to carry out the pending snag list, as long as it was paid, but the Camilleris had refused. On this ground the company was correct to file the action when it had. The court then considered the issue of interest and stated that although in essence this was a commercial agreement, the action was with regard to a debt which was not certain from the very start and required the appointment of a technical expert. Therefore, the court adopted the principle in liquidandis non fit mora and, therefore, interest should start from the date of the judgment. The court ordered the defendants to pay €46,553, which was divided into €18,621 in cash payment and €27,932 in the form of barter. Malcolm Mifsud is a partner at Mifsud & Mifsud Advocates Tribunal gives green light to swimming pools A 2012 planning application for the construction of four swimming pools was turned down by the Environment and Planning Commission after it was held that the pools were to be located outside the boundary of a Category 1 Settlement and within a scheduled Level 4 Area of Ecological Importance. In its conclusions, the Commission underlined that the proposed swimming pools would "compromise the protection and conservation status of a scheduled area", in conflict with Objective 1 of Circular PA1/00 (the policy which regulates ODZ swimming pools and militates against the development of swimming pools "if they will adversely affect valleys and sites of ecological importance". In reaction, the applicant lodged an appeal against the said decision before the Environment and Planning Tribunal, stating that the pools were very small in size and could be safely compared to a Jacuzzi. Moreover, the ODZ pools given the goahead since distant from Robert the valley and screened Musumeci from public view MEPAwatch applicant maintained that each pool was to be contained within the perimeter of a committed cartilage (the boundary of a villa) and not a valley as alleged by the Authority. Moreover, the applicant observed that the pools were located at a distance of only three metres from the rear part of the respective constructed villas. Having said that, the applicant requested the Tribunal to take note of several structures, not YOUR FIRST CLICK OF THE DAY www.maltatoday.com.mt least a number of agricultural reservoirs which had been built in the valley. In turn, the Authority observed that the site under review was granted permission for the demolition of an ODZ farmhouse and the subsequent construction of four two-storey residential units (including basement garages) on condition that no construction took place within the scheduled belt for Wied Ghollieqa. For this reason, the Authority kept on insisting that the area where the pools were proposed should be retained in soil and soft landscaping. In support of his argument, the case officer made reference to current policy, pointing out that ODZ pools "must not adversely affect valleys and/or sites of ecological importance". On a preliminary note, the Tribunal confirmed that the proposed underground pool structures were located within a scheduled buffer zone. Nonetheless, the Tribunal observed that the proposed pools should be located within the perimeter of a committed curtilage, which would serve as a buffer to the distant valley. The Tribunal maintained that the pools were to be enclosed by a low-lying rubble wall and therefore screened completely from public view. Against this background, the Tribunal ruled in favour of the applicant and ordered MEPA to issue the permit subject to fresh designs showing a narrow access around the pool. robert@rmperiti.com

Articles in this issue

Archives of this issue

view archives of MaltaToday previous editions - MT Oct 6 2013